RICHMOND, Va.--(BUSINESS WIRE)--Dominion Energy, Inc. (NYSE: D), today provided several updates for the Coastal Virginia Offshore Wind (CVOW) project. The 2.6 GW, fully permitted project is now ...
Steven D. Ridge, Executive Vice President and CFO, stated that the company "had another strong quarter of execution across each of these priorities," highlighting consistent achievement of financial ...
PORTSMOUTH, Va. — Dominion Energy says its massive Coastal Virginia Offshore Wind (CVOW) project remains on schedule, despite final reviews revealing minor issues that have delayed the start of ...
After receiving its final federal approvals in January, Dominion Energy‘s $9.8 billion Coastal Virginia Offshore Wind project remains on track for completion in late 2026, at which point the ...
WASHINGTON, D.C. (December 22, 2025) – A group of public interest organizations involved in an ongoing lawsuit to stop construction of the massive Virginia offshore wind project are applauding the U.S ...
NORFOLK, Va. — A federal judge has ruled in favor of Dominion Energy, issuing a preliminary injunction in its case challenging the Trump administration's freezing of offshore wind projects. The ...
The first jacket foundation for the substation of the Coastal Virginia Offshore Wind (CVOW) project has departed from the Danish Port of Esbjerg and is on its way to the United States to be installed ...
On March 18, three advocacy organizations and their members filed a lawsuit challenging an offshore wind project against the National Marine Fisheries Service (NMFS) and the Bureau of Ocean Energy ...
Dominion Energy has installed 78 monopile and four offshore substation foundations for as part of the first offshore construction campaign for the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project.